PMI-SP test Format | Course Contents | Course Outline | test Syllabus | test Objectives
The Project Management Institute (PMI) ® offers a professional credential for project schedulers, known as the PMI Scheduling Professional (PMI-SP)®. PMIs professional credentialing examination development processes stand apart from other project management certification examination development practices. PMI aligns its process with certification industry best practices, such as those found in the Standards for Educational and Psychological Testing.
Although many of the domains, tasks, knowledge, and skills outlined by the PMI-SP Examination Content Outline are also covered by the Practice Standard for Scheduling and PMBOK® Guide, there are some that are unique to the PMI-SP Examination Content Outline. Candidates studying for the examination will certainly want to include the current edition of the Practice Standard for Scheduling and PMBOK® Guide as two of their references, and would be well advised to read other current titles on project scheduling.
Schedule Strategy 14%
Schedule Planning and Development 31%
Schedule Monitoring and Controlling 35%
Schedule Closeout 6%
Stakeholder Communications Management 14%
Total 100%
Domain 1: Schedule Strategy (14% of examination)
Task 1 Establish project schedule configuration management policies and
procedures incorporating best practices, regulations, governing standards
and organization policies, and procedures to ensure accessibility, storage,
retrieval, maintenance, change control, and baseline schedule control.
Task 2 Develop schedule approach, based on the unique characteristics of the
project, including enterprise environmental factors and organizational
process assets, in order to define schedule requirements.
Task 3 Establish scheduling policies and procedures regarding methodology,
selection of a scheduling tool, scheduling parameters, performance
thresholds, activity granularity, presentation format, earned value
management (EVM) implementation, analysis techniques, and approval
requirements by using resources such as organizational process assets and
project documents in order to develop the schedule management plan and
standardize operational procedures.
Task 4 Develop the scheduling-related components for project management plans
(for example, integration, scope, cost, quality, resources, communication,
risk, and procurement management), through review of contract
requirements, in order to integrate scheduling activities into the overall
project management process.
Task 5 Provide information about project scheduling objectives and goals, the role of
the scheduler, and scheduling procedures to project team members to
facilitate effective participation in the project.
Knowledge and Skills:
Applicable contract requirements, regulations, and governing standards
Schedule control processes (for example, baseline control, status update procedure, variance thresholds)
Scheduling development concepts (for examples, coding, work breakdown structures, organizational breakdown structure, resource breakdown structures)
Project charter
Domain 2: Schedule Planning and Development (31% of examination)
Task 1 Develop the work breakdown structure (WBS), organizational breakdown
structure (OBS), control accounts (CA), and work packages through
communication with subject matter experts and stakeholders and analysis of
the contractual commitments in order to ensure completion of the project
scope.
Task 2 Define activities and milestones through communication with subject matter
experts, decomposition, and application of scheduling policies and
procedures to identify and document the work to be performed.
Task 3 Estimate activity durations, utilizing subject matter experts and scheduling
techniques such as three-point estimate, parametric, analogous and/or
Program Evaluation and Review Technique (PERT) in order to develop an
overall schedule model.
Task 4 Sequence activities, incorporating defined dependencies (internal, external,
and cross programs) milestones, and constraints (for example, calendars,
geography, contracts), in order to develop a logical, dynamic schedule model.
Task 5 Identify critical and near-critical path(s) using techniques such as Critical
Path Method, Critical Chain, Program Evaluation and Review Technique
(PERT), and Monte Carlo simulation in order to meet project delivery date
requirements.
Task 6 Develop the project resource breakdown structure (RBS), determine resource
availability, and assign resources to activities by working with functional
managers, project managers, and project team members in order to define the
resource constrained schedule.
Task 7 Adjust schedule model based upon resource availability, available budget,
and other known constraints in order to calculate the resource constrained
schedule.
Task 8 Align schedule with the overall program plan or integrated master plan (IMP),
through review of enterprise objectives and contract documentation, in order
to ensure accomplishment of overall program objectives.
Task 9 Analyze major milestones against statement of work (SOW), the contract,
and/or memorandum of understanding, to assess whether schedule model
delivery estimates meet required deadlines.
Task 10 Perform schedule risk analysis using quantitative tools or techniques (for
example, what-if scenarios, Monte Carlo simulation) in order to determine if
project milestone dates are achievable within acceptable risk tolerances.
Task 11 Obtain a consensus of the project customer, sponsor, project manager, and
project team members, in order to establish an approved baseline schedule.
Task 12 Establish the Performance Measurement Baseline (PMB), using organizational
processes and standard techniques, in order to enable performance measurement and management.
Knowledge and Skills:
Scope statements, including deliverables and deadlines
Work breakdown structure (WBS)
Organizational breakdown structure (OBS)
Resource breakdown structure (RBS)
Cost structure as related to schedule development
Activity definition
Activity execution techniques (duration/time, effort/work)
Dependency relationship types (Finish to Start, Start to Finish, Finish to Finish, Start to Start)
Leads and lags
Prioritization within the schedule model
Resource groups
Resource calendars
Resource allocation techniques
Activity Network Diagram (AND)
Precedence Diagramming Method (PDM)
Capacity requirements/resource requirements
Contingency reserve or buffer (funds, budget, or time)
Cost and schedule integration
Schedule baselining
Performance Measurement Baseline (PMB)
Inter-project Dependencies
Milestone definition
Schedule model components
Schedule risk-assessment techniques (for example, Monte Carlo simulation, PERT)
Domain 3: Schedule Monitoring and Controlling (35% of examination)
Task 1 Collect activity status at defined intervals from activity owners via reports,
meetings, inspections, or other standard procedures in order to update and
review the project progress.
Task 2 Collect resource information and updates via reports, timesheets, meetings,
inspections, or other standard procedures in order to report on resource
utilization and availability.
Task 3 Perform schedule analysis and audit, on in-house and subcontractor
schedules, using industry standards, guidelines and best practices in order to
identify and report project schedule, status, changes, impacts or issues.
Task 4 Identify alternative project execution options, using tools and techniques
such as what-if scenario analyses, in order to optimize the schedule.
Task 5 Incorporate approved risk mitigation activities into the schedule, by utilizing
defined change control processes, in order to establish a new performance
measurement baseline (PMB).
Task 6 Update the schedule model and document schedule baseline changes,
received through formal change-control processes, in order to maintain an
accurate schedule and facilitate forensic schedule analysis, if required.
Knowledge and Skills:
Progress measurement techniques (for example, percent complete, actual/remaining duration, estimate to complete)
Industry standards, guidelines, and best practices with respect to activity status update frequency, format, and content
Metrics to monitor, analyze, and control the schedule
Cost and schedule reserve analysis
Activity prioritization
Available data, logical data organization/relationships within data elements
Electronic file storage and retrieval standards
Resource breakdown structure (RBS)
Resource calendars
Resource groups
Resource allocation techniques
Schedule risk analysis
Project schedule change control
Reserve analysis
Knowledge of ongoing audit analysis
Activity Network Diagram (AND)
Precedence Diagramming Method (PDM)
Schedule risk assessment techniques (for example, Monte Carlo simulation, Program and Evaluation Review Technique [PERT])
Schedule and cost variance management
Domain 4: Schedule Closeout (6% of examination)
Task 1 Obtain final acceptance of the contractual schedule components, by working
with sponsor and/or customer, in order to facilitate project closeout.
Task 2 Evaluate final schedule performance against baseline schedule, scheduling
approach and the implementation, using standard scheduling tools and
techniques, including solicitation of feedback from stakeholders, in order to
identify lessons learned and develop best practices.
Task 3 Update the organizational process assets, through documentation of
identified lessons learned and best practices, in order to Improve business
processes.
Task 4 Distribute final schedule reports, including earned value management (EVM)
calculations and variance analysis, to stakeholders in order to facilitate
project closeout.
Task 5 Archive schedule files (for example, final schedule model, schedule
management plan, periodic status reports, schedule change log), as per
defined procedures in order to satisfy contractual requirements and prepare
for potential forensic schedule analysis.
Knowledge and Skills:
Contractual schedule components
Schedule close-out procedures
Feedback techniques
Schedule review techniques
Schedule issue management
Transition planning
Domain 5: Stakeholder Communications Management (14% of examination)
Task 1 Develop and foster relationships with project stakeholders, consistent with
the communication management plan, in order to enhance support for the
project schedule.
Task 2 Generate and maintain visibility of project schedule, by working with the
project manager and/or stakeholders, in order to maintain stakeholder
support.
Task 3 Provide senior management and other stakeholders with verbal and written
schedule status updates and impact on schedule of corrective actions, as
defined by the communication management plan, in order to maintain
stakeholder awareness.
Task 4 Communicate schedule issues that could impact delivery of project scope or
adherence to the schedule management plan, in order to elevate awareness to
relevant stakeholders.
Knowledge and Skills:
Targeting communications to senior management
Methods and techniques used to maintain visibility of project schedule Elements of the communication management plan Oral and written communication tools and techniques
Targeting communications to intended audience
Presentation tools and techniques
Negotiation
Facilitation
Cultural sensitivity and diversity
Conflict resolution
Project life cycle
Stakeholder-impact analysis
Change management/control
Scheduling terminology
Organizational process assets
Project management software
Project management information systems
Schedule documentation and reporting techniques
Scheduling data management procedures (for example, archiving, storage, retrieval)
Estimation techniques (for example, analogy based estimation, parametric estimation, historical data, expert estimation)
Scheduling methods (for example, critical path method, critical chain, linear, agile)
Scheduling techniques (for example, resource leveling, schedule compression, simulation)
Earned Value Management (EVM)
Gantt Charts
Quantitative and qualitative schedule analysis (for example, schedule performance index, baseline execution index, float analysis)
Problem-solving tools and techniques
Contract schedule requirements
100% Money Back Pass Guarantee

PMI-SP PDF sample Questions
PMI-SP sample Questions
PMI-SP Dumps
PMI-SP Braindumps PMI-SP test questions PMI-SP Practice Test
PMI-SP genuine Questions
PMI
PMI-SP
PMI Scheduling Professional
https://killexams.com/pass4sure/exam-detail/PMI-SP
QUESTION: 311
A company hires a scheduler for one of its projects. What skills should he possess to efficiently work with the project team? Each correct answer represents a complete solution. Choose three.
1. Performance control
2. Execution scheduling
3. Leadership
4. Feasibility planning
Answer: D, B, A
Explanation:
A scheduler schedules the constraints for the project into phases with respect to the time and resources available. He can be hired from outside a company, or from within a company. The basic roles of a scheduler are as follows: Feasibility Planning: A scheduler is the time management expert who paints a picture of the project. He develops a strategy for delivery and to gain consensus. Execution Schedule: A scheduler works with the project team to optimize and refine the schedule until an agreed schedule has been developed. Performance Control: A schedule is maintained by the scheduler who optimizes outcomes and instructs the project team on their presentation. It is important that the scheduler be aware of the changes and trends related to the project delivery. Answer option C is incorrect. This is the skill possessed by the project manager.
QUESTION: 312
Which of the following is NOT an output of the control schedule process?
1. Organizational process assets
2. Change requests
3. Project termination request
4. Project document updates
Answer: C
Explanation:
The project termination request is not an output of the control schedule. Early termination of a project is a closing process and usually does not stem from the project manager. The outputs of the control schedule process are as follows: Work Performance Measurements: The work packages and control accounts are documented and communicated to the stakeholders. Organizational Process Assets Updates: The assets that are updated are: corrective actions chosen and the reasons, causes of variance, and other types of lessons learned from project schedule control. Change Requests: It is processed for reviews and disposition through the
Perform Integrated Change Control process. Project Management Plan Updates: The elements that need to be updated are: schedule baseline, schedule management plan, cost baseline. Project Document Updates: The elements that need to be updated in project document updates are: schedule data and project schedule.
QUESTION: 313
You are the project manager of the NHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day for the early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but you must be careful not to increase project risk beyond an acceptable level of risk exposure. Which of the following approaches is most likely to increase project risk?
1. Using the critical chain method
2. Crashing
3. Adding leads to the project work
4. Fast tracking
Answer: D
Explanation:
Fast tracking allows entire phases of the project to overlap and this action does increase risks. This is an approach that you would want to avoid in your project. Answer option B is incorrect.
Crashing adds labor to the project and typically drives project costs. Answer option A is
incorrect. The critical chain method considers the availability of project resources as part of its network diagramming technique. Answer option C is incorrect. Lead time allows project activities to overlap and may introduce project risks, but not to the extent of using fast tracking.
QUESTION: 314
You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone, which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend
$2,073,654. What is this project's planned value?
A. $2,025,000
B. There is not enough information to know C. $4,500,000
D. $2,250,000
Answer: D
Explanation:
The planned value is the worth of the project if it were on time. In this instance, the project should be 50 percent complete, so the planned value is half of the project budget - $2,250,000. Planned value (PV) is the authorized budget assigned to the schedule work to be accomplished for a schedule activity or work breakdown structure component. It serves as a baseline against which genuine performance is measured. The theory of planned value is of vital importance to the project management team and it is important to keep careful track of this. The term planned value can also be in some situations referred to by the project management team and the project management team leader as the budgeted cost of work scheduled (BCWS). Answer option C is incorrect. This is the budget at completion. Answer option A is incorrect. This is the earned value for the project. Answer option B is incorrect. There is enough information to know.
QUESTION: 315
You are the project manager for your organization. You want to record some details about the work that the project team has to complete. You want to document the level of effort, where the work is to be performed, and the person who will be responsible for completing the work. Which of the following is the best place to document this information?
1. Activity attributes
2. Project management plan
3. Schedule Management Plan
4. Roles and Responsibilities Matrix
Answer: A
Explanation:
The activity attributes initially include the Activity ID, WBS ID, and the Activity Name, but it can evolve over time to include other components about the work. Activity attributes are an output of the Define Activity process. These attributes refer to the multiple components that frame up an activity. The components for each activity during the early stages of the project are the Activity ID, WBS ID, and Activity name. At the later stages, the activity attributes include Activity codes, Predecessor activity, activity description, logical relationship, successor activity, leads and lags, imposed dates, and constraints and assumptions. Activity attributes are used for schedule development and for ordering, selecting, and sorting the planned schedule activities in a number of ways within reports. Answer option B is incorrect. A project management plan is a formal document that defines how the project is being monitored, controlled, and executed. It is not the best answer. Answer option D is
incorrect. The roles and responsibilities matrix records the work and the person to record the work, but does not offer additional information such as locale for the work, level of effort, and other information. Answer option C is incorrect. The Schedule Management Plan defines how the schedule will be created, executed, and controlled.
QUESTION: 316
Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers would like weekly status reports on how the project is performing. Where should Steve document this information?
1. Communications management plan
2. Issues log
3. Project schedule
4. Schedule management plan
Answer: A
Explanation:
The communications management plan defines who needs what information, when the information is needed, and the modality the information is expected in. Answer option C is incorrect. The project schedule could include project management activities such as schedule communication, but the communications management plan is the best answer as this information is absolutely documented in this plan. Answer option D is incorrect. The schedule management is not the best location for this information. Answer option B is incorrect. The request for customer communication is not an issue, so this choice is not the most appropriate.
QUESTION: 317
Jenny is the project manager for her organization. Her project is not doing well on project schedule performance, and management wants her to predict how the project schedule and cost will end. Management has asked Jenny to report and forecast her project's performance based on the Judgmental methods. Which of the following judgmental methods will Jenny use to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.
1. Forecast by analogy
2. Technology forecasting
3. Autoregressive moving average
4. Scenario building
Answer: D, B, A
Explanation:
The judgmental forecasting method incorporates intuitive judgments, opinions and subjective probability estimates. Some examples of judgmental forecasting are as follows: Composite forecasts Surveys Delphi method Scenario building Technology forecasting Forecast by analogy
Answer option C is incorrect. Autoregressive moving average is an example of the causal/econometric method.
QUESTION: 318
You work as a project manager for BlueWell Inc. You are creating the activity list for the project. The activity list is based on the work packages defined in the project's WBS. Activities provide a basis for all of the following information except for which one?
1. Scope baseline
2. Executing
3. Scheduling
4. Estimates
Answer: A
Explanation:
The project's scope baseline is not derived or provided by the project's activity list. The scope baseline is made of the project's WBS, WBS Dictionary, and the Project Scope Statement. The activity list provides for estimating, scheduling, executing, and monitoring and controlling the project work. The scope baseline is an element of the project management plan. The contents of the scope baseline include the following: Project scope statement: It includes the product scope description and the project deliverables, and defines the product user acceptance criteria. WBS: It defines each deliverable and the decomposition of the deliverables into work packages. WBS
dictionary: It contains the detailed description of work and technical documentation for each
WBS element. Answer option D is incorrect. Estimates do provide a basis for creating time and cost estimates. Answer option B is incorrect. Activities are executed in the project. Answer option C is incorrect. Activities are scheduled as part of project planning.
QUESTION: 319
Tom is the project manager of the GHQ Project for his organization and he is working on recovering the project schedule. As Tom examines his schedule, he is especially aware of project activities with hard logic. What is hard logic?
1. Hard logic describes activities that can be completed in any order but are positioned with finish-to-start relationships.
2. Hard logic describes activities that have external constraints, such as a vendor.
3. Hard logic describes activities that must be completed in a particular order unless additional resources with comparable skill sets can be added to the project.
4. Hard logic describes activities that must be completed in a particular order.
Answer: D
Explanation:
Hard logic, also known as mandatory dependencies, describes activities that must be completed in a particular order. Hard logic is a binding connection between activities. It is also known as mandatory dependency or hard dependency. Hard logic requires activities to take place in a specific order according to the nature of work. It is a well-built connection where an activity cannot start until and unless a previous one is completed. There are also substantial hard logic connections where soft logic does not usually apply. Several activities rely on hard logic for the successful completion of the project. Answer options B, A, and C are incorrect. These are not a valid description of hard logic.
QUESTION: 320
You are the project manager for your organization. You are working with your project team to create the schedule baseline for your project. You will also be creating the schedule data for this project. The schedule data typically includes all of the following except for which one?
1. Risk activities
2. Schedule activities
3. Activity attributes
4. Schedule milestones
Answer: A
Explanation:
Risk activities are not part of the schedule data. Risk is documented in the risk register, and monitored and controlled throughout the project. In some instances, risk may be part of the activity attributes. The schedule data includes the schedule milestones, schedule activities, activity attributes, and the assumptions and constraints. The schedule data includes the schedule activities, schedule milestones, activity attributes, and documentation of all known assumptions and constraints. The sum of additional data varies by application area. The schedule data commonly supplied as supporting details includes: Resource requirement by time period, frequently in the category of histogram Alternative schedules, such as best case or worst case, or resource leveled, with or without imposed dates Scheduling of contingency reserves Answer option D is incorrect. Schedule milestones are part of the schedule data. A Answer option B is incorrect. Schedule activities are part of the schedule data. Answer option
C is incorrect. Activity attributes are part of the schedule data.
QUESTION: 321
Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member,
reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:
If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?
1. The project will complete on time.
2. The project will be late by one day.
3. The project will be late by two days.
4. The project will be early by two days.
Answer: Pending. Please send your suggestions to support@
QUESTION: 322
Which of the following provides a method to track project progress during project execution against what was planned?
1. Team members profile
2. Benefit-cost ratio
3. Schedule baseline
4. Detailed project budget
Answer: C
Explanation:
A schedule baseline provides a method to track project progress during project execution against what was planned.
What is schedule baseline?
Schedule baseline is a project schedule used in measuring project progress. It helps provide a comparison with the genuine progress of work against the schedule and to determine if performance to date is within acceptable parameters. Any change caused by change in scope of the project invalidates the original schedule and requires a new baseline schedule. Answer
options D, A, and B are incorrect. A detailed project budget, team members profile, and benefit- cost ratio will not help you track project progress.
What is BCR?
A benefit-cost ratio (BCR) is an indicator, used in the formal discipline of cost-benefit analysis, that attempts to summarize the overall value for money of a project or proposal. A BCR is the ratio of the benefits of a project or proposal, expressed in monetary terms, relative to its costs, also expressed in monetary terms. All benefits and costs should be expressed in discounted present values. For e.g., a BCR of $3.8 indicates a payback of $3.8 for each dollar expended.
QUESTION: 323
You have been hired as a contract project manager for Tech Perfect Inc. The project has already been started. Sufficient details of the project have already been structured. You are working with your team for cost estimation of the project. Which of the following estimating techniques will you use for the highest degree of accuracy?
1. Parametric modeling
2. Analogous
3. Top-down
4. Bottom-up
Answer: D
Explanation:
According to the question, you have to use the estimating technique that has a higher degree of
accuracy. The most accurate estimating technique is bottom-up estimating. What is bottom-up estimating?
Bottom-up is a cost estimating technique that involves estimating the cost of individual work
packages or schedule activities with the lowest level of detail. The detailed cost is rolled up (or summarized) to higher levels for total project estimates. This summarized data is very useful for reporting and tracking purposes. Bottom-up estimating provides a higher degree of accuracy, provided the estimates at the work package level are accurate. Answer options C, A, and B are incorrect. Parametric modeling and analogous estimating techniques use top-down estimation model. These are less accurate than the bottom-up estimation.
What is analogous estimating?
Analogous is an estimating technique that uses the values of parameter, such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous, similar activity as the basis for estimation of the same parameter for a future activity. It is a top- down estimating technique and is a form of expert judgment. It provides a lower degree of accuracy than other estimating techniques. This technique is primarily used when there is a limited amount of detailed information about the project or program.
What is parametric modeling?
Parametric modeling is an estimating technique that uses parameters, or project characteristics, to forecast project costs. It involves a top-down approach and is similar but more accurate than analogous estimating. It uses historical data and other variables to calculate an estimate for activity parameters, such as scope, cost, budget, and duration.
QUESTION: 324
Beth is the project manager of the KJH project. Sarah is Beth's administrative assistant and Ben is the project team leader. Beth's project has eight virtual teams throughout the world that will be working on the activities relevant to the deliverables in their locales. Thomas, the project sponsor, has told Beth that he is to be kept abreast of all communication between her project and the stakeholders. In this project, who is the lead person responsible for communication with all stakeholders?
1. Thomas
2. Sarah
3. Each of the team leaders for the eight virtual teams
4. Beth
Answer: D
Explanation:
Beth, the project manager, is responsible for communication with all stakeholders. According to the PMBOK, the project manager occupies the center of the interactions between stakeholders
and the project itself. Answer option B is incorrect. Sarah may help with the communications,
but she is not responsible for the communications. Answer option A is incorrect. Thomas, the project sponsor, just needs to be kept abreast of the information. Answer option C is incorrect. The project team leaders for the virtual sites are not responsible for communicating with the project stakeholders.
QUESTION: 325
What project management plan will document the time frame and frequency for the distribution of required information?
1. Scope Management Plan
2. Communications Management Plan
3. Stakeholder Management Plan
4. Schedule Management Plan
Answer: B
Explanation:
The project's Communications Management Plan defines what information will be distributed, when it will be distributed, to whom it will be distributed, and the modality of the information. Answer option D is incorrect. The Schedule Management Plan defines the project work, when the project work will happen, resource utilization, and how the schedule will be monitored and controlled. Answer option C is incorrect. There is a stakeholder management strategy, but not a Stakeholder Management Plan. Answer option A is incorrect. The project's Scope Management Plan defines how the scope will be created, how the changes will be allowed, how the scope will be executed, monitored and controlled, and finally closed.
QUESTION: 326
Fill in the blank with the appropriate word. When activities are logically linked, they become the .
Answer: Schedule.
Explanation:
An activity is an individual element of work that is logically linked to other activities to form the schedule. Its primary characteristics include an overall duration based upon the resources applied to it (manpower, material, and equipment), as well as a start and completion date that is tied to a work calendar. It also has a relationship with other activities (predecessors and successors).
QUESTION: 327
Examine the figure given below.
In this project network diagram, what is the total float for Activity I?
1. Three
2. Zero
3. Five
4. One
Answer: A
Explanation:
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for Activity I is Day 20. Therefore, the difference of the early start and the late start reveals the float as three days. It is possible, and acceptable, to use the difference of the early finish and the late finish to find the float, as the value will be the same amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total float.
Killexams VCE test Simulator 3.0.9
Killexams has introduced Online Test Engine (OTE) that supports iPhone, iPad, Android, Windows and Mac. PMI-SP Online Testing system will helps you to study and practice using any device. Our OTE provide all features to help you memorize and practice test Braindumps while you are travelling or visiting somewhere. It is best to Practice PMI-SP test Questions so that you can answer all the questions asked in test center. Our Test Engine uses Questions and Answers from genuine PMI Scheduling Professional exam.
Online Test Engine maintains performance records, performance graphs, explanations and references (if provided). Automated test preparation makes much easy to cover complete pool of questions in fastest way possible. PMI-SP Test Engine is updated on daily basis.
Recently read PMI PMI-SP PDF Download for test
At killexams.com, we offer valid and current PMI PMI-SP Latest Questions available for instant download with a single click. Avoid wasting time on unreliable free materials. Register with a minimal payment to activate your PMI Scheduling Professional Mock Questions download account in minutes. Study our premium PMI-SP Cram Guide practice test materials, accessible via Online Test Engine or Desktop Test Engine, and confidently pass your exam.
Latest 2025 Updated PMI-SP Real test Questions
Discover our premium PMI-SP examination questions and solutions PDF Download in two convenient formats: PMI-SP PDF files and PMI-SP VCE examination simulator. Ace the full PMI PMI-SP real test swiftly and effectively. The PMI-SP exam preparation software PDF format is accessible on any device, allowing you to print PMI-SP PDF Download to craft your personalized study guide. Boasting an impressive pass rate of 98.9%, our PMI-SP practice test aligns closely with the real test, delivering a 98% success rate. Ready to triumph in the PMI-SP test on your first attempt? Visit killexams.com to experience the PMI PMI-SP real examination today. At killexams.com, we provide superior study materials and practice questions to empower your preparation for the PMI-SP certification exam. Our dedicated expert team continuously updates the PMI-SP Free test PDF to ensure you access the most current and precise questions. With our comprehensive study resources and advanced test simulators, including online and desktop test engines, you can approach the PMI-SP test with confidence and achieve success in just one attempt. Do not delay—visit killexams.com now to embark on your path to becoming a certified PMI-SP professional.
Tags
PMI-SP Practice Questions, PMI-SP study guides, PMI-SP Questions and Answers, PMI-SP Free PDF, PMI-SP TestPrep, Pass4sure PMI-SP, PMI-SP Practice Test, download PMI-SP Practice Questions, Free PMI-SP pdf, PMI-SP Question Bank, PMI-SP Real Questions, PMI-SP Mock Test, PMI-SP Bootcamp, PMI-SP Download, PMI-SP VCE, PMI-SP Test Engine
Killexams Review | Reputation | Testimonials | Customer Feedback
My test experience with Killexams.com was unforgettable. Their team was encouraging, and their reasonably priced questions gave me the confidence to achieve a high score. I highly recommend them.
Richard [2025-5-13]
Killexams.com provided the high-quality guidance I needed to excel in the PMI-SP exam. The engaging presentation of syllabus enhanced my understanding, making my preparation much smoother. Thanks to their support, I was able to achieve an excellent score.
Martha nods [2025-5-23]
Killexams.com is outstanding in every aspect. The PMI-SP study guide is comprehensive, providing the latest updates and real test questions, allowing you to focus on what matters most. I used their test simulator extensively, which gave me the confidence to face the genuine test with ease. Investing in Killexams.com was undoubtedly a wise decision for my career, and I am thrilled to have passed the PMI-SP test with flying colors. I have added my certification to my resume and LinkedIn profile, which has helped boost my professional reputation.
Martin Hoax [2025-4-1]
More PMI-SP testimonials...
PMI-SP Exam
User: Natalyah*****![]() ![]() ![]() ![]() ![]() Last week, I passed my pmi-sp test with killexams.com’s testprep practice tests, which also prepared me for another test this month. Their materials were a fantastic way to enhance my expertise, and I was relieved to know all the answers to the many familiar questions. I am confident in recommending their resources to others. |
User: Harraz*****![]() ![]() ![]() ![]() ![]() Both my roommate and I agree—Killexams.com is the best for pmi-sp test prep. We both passed with terrific scores, and I highly recommend their services. |
User: Eugene*****![]() ![]() ![]() ![]() ![]() With only a short preparation period, killexams.com’s practice questions helped me score 88% on the pmi-sp exam. The correctly structured Braindumps were perfect for my needs, ensuring a successful outcome. |
User: Saanvi*****![]() ![]() ![]() ![]() ![]() Killexams.com is an outstanding platform for IT test preparation, offering precise and reliable materials for the PMI-SP exam. Their practice questions were spot-on, covering exactly what I needed to know, and the test simulator provided a realistic test experience. My friends have also used killexams.com for certifications like Cisco and Microsoft, and we all agree it’s the best resource available. |
User: Fred*****![]() ![]() ![]() ![]() ![]() I purchased the online mock test for the PMI-SP test and passed it on my very first attempt. I am so grateful for the help provided by Killexams.com. I scored 98%, which is a huge accomplishment for me. The Killexams.com team is wonderful, and I sincerely hope they continue to update their questions and maintain their excellent work. |
PMI-SP Exam
Question: Does PMI-SP test prep improves the knowledge? Answer: PMI-SP test prep contain genuine questions and answers. By reading and understanding the complete dumps questions greatly improves your knowledge about the core syllabus of the PMI-SP exam. It also covers the latest PMI-SP syllabus. These PMI-SP test questions are taken from genuine test sources, that's why these PMI-SP test questions are sufficient to read and pass the exam. Although you can use other sources also for improvement of knowledge like textbooks and other aid material these PMI-SP questions are sufficient to pass the exam. |
Question: Do I need internet connection to read killexams dumps? Answer: No, you need not be online all the time to study for your exam. Killexams.com provides an offline method by downloading your PMI-SP test questions in PDF format on your mobile phone, iPad or laptop and carry them anywhere you like. You do not need to be online all the time to keep your study going. Killexams test simulator also works offline. Just download and install on your laptop and you can go anywhere to keep your study going and preparing your test at a tourist or healthier place. Whenever you need to re-download the test files, you can connect your computer to the internet and download and go offline anytime you like. |
Question: The same PMI-SP questions in the genuine test, Is it possible? Answer: Yes, It is possible and it is happening in the case of these PMI-SP test questions. They are taken from genuine test sources, that's why these PMI-SP test questions are sufficient to read and pass the exam. Although you can use other sources also for improvement of knowledge like textbooks and other aid material these PMI-SP questions are sufficient to pass the exam. |
Question: How long prep is required to pass PMI-SP exam? Answer: If you have more time to study, you can practice more with PMI-SP questions and get ready to take the test in 24 to 48 hours. But we recommend taking your time to study and practice PMI-SP practice test until you are sure that you can answer all the questions that will be asked in the genuine PMI-SP exam. |
Question: How long I need to exercise PMI-SP questions? Answer: It is up to you. If you are free and you have more time to study, you can prepare for an test even in 24 hours. But we recommend taking your time to study and practice PMI-SP practice test until you are sure that you can answer all the questions that will be asked in the genuine PMI-SP exam. |
References
PMI Scheduling Professional PDF Download
PMI Scheduling Professional test preparation software
PMI Scheduling Professional boot camp
PMI Scheduling Professional PDF Download
PMI Scheduling Professional practice test software
PMI Scheduling Professional practice test software
PMI Scheduling Professional test practice tests
PMI Scheduling Professional Real test Questions
PMI Scheduling Professional PDF Download
PMI Scheduling Professional test prep questions
Frequently Asked Questions about Killexams Practice Tests
How much PMI-SP test and vce practice test cost?
You can see all the PMI-SP test price-related information from the website. Usually, discount coupons do not stand for long, but there are several discount coupons available on the website. Killexams provide the cheapest hence up-to-date PMI-SP dumps questions that will greatly help you pass the exam. You can see the cost at https://killexams.com/exam-price-comparison/PMI-SP You can also use a discount coupon to further reduce the cost. Visit the website for the latest discount coupons.
Which is best certification training website?
Killexams is the best of all certification training websites that provide up-to-date and valid test questions with practice questions for the training of candidates to pass the test at the first attempt.
Which website provide valid TestPrep?
Killexams is the best certification brainpractice questions website that provides up-to-date and 100% valid test questions with practice tests. These VCE practice questions are very good for test practice to pass the test on the first attempt. Killexams team keeps on updating the test practice questions continuously.
Is Killexams.com Legit?
Sure, Killexams is 100% legit and fully trusted. There are several options that makes killexams.com unique and genuine. It provides exact and completely valid test dumps filled with real exams questions and answers. Price is surprisingly low as compared to many of the services online. The Braindumps are modified on regular basis using most exact brain dumps. Killexams account set up and product or service delivery is really fast. Data file downloading is unlimited and fast. Support is available via Livechat and Contact. These are the characteristics that makes killexams.com a robust website that provide test dumps with real exams questions.
Other Sources
PMI-SP - PMI Scheduling Professional cheat sheet
PMI-SP - PMI Scheduling Professional test contents
PMI-SP - PMI Scheduling Professional book
PMI-SP - PMI Scheduling Professional test dumps
PMI-SP - PMI Scheduling Professional real questions
PMI-SP - PMI Scheduling Professional test success
PMI-SP - PMI Scheduling Professional dumps
PMI-SP - PMI Scheduling Professional Practice Test
PMI-SP - PMI Scheduling Professional Practice Test
PMI-SP - PMI Scheduling Professional syllabus
PMI-SP - PMI Scheduling Professional test Cram
PMI-SP - PMI Scheduling Professional tricks
PMI-SP - PMI Scheduling Professional answers
PMI-SP - PMI Scheduling Professional test
PMI-SP - PMI Scheduling Professional test Questions
PMI-SP - PMI Scheduling Professional outline
PMI-SP - PMI Scheduling Professional test Braindumps
PMI-SP - PMI Scheduling Professional information source
PMI-SP - PMI Scheduling Professional Free PDF
PMI-SP - PMI Scheduling Professional study help
PMI-SP - PMI Scheduling Professional test prep
PMI-SP - PMI Scheduling Professional Study Guide
PMI-SP - PMI Scheduling Professional Cheatsheet
PMI-SP - PMI Scheduling Professional course outline
PMI-SP - PMI Scheduling Professional test Braindumps
PMI-SP - PMI Scheduling Professional genuine Questions
PMI-SP - PMI Scheduling Professional Questions and Answers
PMI-SP - PMI Scheduling Professional test
PMI-SP - PMI Scheduling Professional test Cram
PMI-SP - PMI Scheduling Professional exam
PMI-SP - PMI Scheduling Professional information source
PMI-SP - PMI Scheduling Professional PDF Braindumps
PMI-SP - PMI Scheduling Professional questions
PMI-SP - PMI Scheduling Professional guide
PMI-SP - PMI Scheduling Professional Practice Questions
PMI-SP - PMI Scheduling Professional boot camp
PMI-SP - PMI Scheduling Professional questions
PMI-SP - PMI Scheduling Professional test
PMI-SP - PMI Scheduling Professional information hunger
PMI-SP - PMI Scheduling Professional study help
PMI-SP - PMI Scheduling Professional cheat sheet
PMI-SP - PMI Scheduling Professional Question Bank
PMI-SP - PMI Scheduling Professional test dumps
PMI-SP - PMI Scheduling Professional Study Guide
Which is the best testprep site of 2025?
Discover the ultimate test preparation solution with Killexams.com, the leading provider of premium practice test questions designed to help you ace your test on the first try! Unlike other platforms offering outdated or resold content, Killexams.com delivers reliable, up-to-date, and expertly validated test Braindumps that mirror the real test. Our comprehensive dumps questions is meticulously updated daily to ensure you study the latest course material, boosting both your confidence and knowledge. Get started instantly by downloading PDF test questions from Killexams.com and prepare efficiently with content trusted by certified professionals. For an enhanced experience, register for our Premium Version and gain instant access to your account with a username and password delivered to your email within 5-10 minutes. Enjoy unlimited access to updated Braindumps through your download Account. Elevate your prep with our VCE practice test Software, which simulates real test conditions, tracks your progress, and helps you achieve 100% readiness. Sign up today at Killexams.com, take unlimited practice tests, and step confidently into your test success!
Important Links for best testprep material
Below are some important links for test taking candidates
Medical Exams
Financial Exams
Language Exams
Entrance Tests
Healthcare Exams
Quality Assurance Exams
Project Management Exams
Teacher Qualification Exams
Banking Exams
Request an Exam
Search Any Exam